Wednesday, December 10, 2008

Topsoil


I had figured the next step for natural gas would be after the 4-way inspection, but the gas guy on the HVAC crew told me I should order the yard line now, so that we'll be ready to order the meter when the 4-way is done. I called Questar, and found out they won't lay the yard line until we're up to finished grade on that side of the house. I couldn't believe they were really unwilling to dig a trench until I brought in more dirt, but that's what they said, so we did. We got a great deal on some topsoil from the new Station Park development over by the freeway where they've removed several inches of the farm soil and have to get rid of it to build all the fancy-pants new stores and stuff.